Wednesday, December 16, 2009
We Almost Passed Our First Inspection!
Because the new casita is going to be slab on grade, the plumber needed to come in and rough in all the waste lines before they can pour the concrete. He worked in the mud for about a day to get all the waste lines and vent stacks in. When the inspector came by, he almost passed us! Apparently he wanted a small change that wasn't enough to warrant stopping forward progress. The plumber came back that afternoon to make the change, and the inspector will sign it off when he comes to inspect the forms before the pour.
To get a feel for the finished level of the floor, look at the big black boxy thing in the above picture. That is where the tub drain is going to be, and the whole box will be under the slab.
The surveyors came back to double check the forms and produce a certification letter to prove to the city that everything is where it should be -- let's hope it actually is!